Go-live week is where the project plan meets the shop floor, and the shop floor usually wins the first three days. Here's what actually happened during one mid-…
Go-live week is where the project plan meets the shop floor, and the shop floor usually wins the first three days. Here's what actually happened during one mid-market manufacturer's Business Central cutover.
Day one is a support desk, not a victory lap
The best-prepared teams staffed a physical help desk on the production floor for the first 72 hours. Every question answered in person was a support ticket that never existed.
The project team had planned for a celebratory kickoff meeting on day one. It got cancelled within the first hour, once it became clear everyone with implementation knowledge needed to be on the floor instead.
By day five, ticket volume had dropped by more than half — not because the system got easier, but because the team got faster at recognizing the same five questions.
What actually made week two different
By the second week, the physical help desk had turned into a rotating schedule of two "super users" per shift — production employees who'd been trained a level deeper than everyone else and could resolve most questions without escalating.
That structure outlasted the go-live. Six months later, those same super users were still the first line of support, and formal IT tickets had dropped to a fraction of what they were during the transition itself.